SIOP Overview
19 minutes 12 seconds
Masterclass
The monthly plan, in one sitting. Demand, supply, and the sign-off.
The Profitable Growth Operating System
Opening this screen.
November 2026 · one monthly plan
Sales, inventory, and operations planning is its own monthly meeting. Demand, supply, and stock are one plan, in units and dollars. A dollar reaches the Profit Bridge only when the owner approves a measured effect on throughput, working capital, or service level.
SIOP is the short name. This page is the monthly plan for what you will sell, what you can make, and what you will hold. Nothing here posts until you approve a measured dollar.
19 minutes 12 seconds
Masterclass
The monthly plan, in one sitting. Demand, supply, and the sign-off.
10 minutes 19 seconds
Masterclass
Lock the forecast the company can sell.
13 minutes 21 seconds
Masterclass
Name the capacity, the bottleneck, and the supplier lead time.
8 minutes 23 seconds
Masterclass
Turn the plan into cash, inventory, and the month you can sign.
9 minutes 42 seconds
Masterclass
Who owns the month, and who signs it.
14 minutes 44 seconds
Masterclass
The numbers and the file the monthly plan reads.
This is the book for SIOP.
Ebook, workbook, and audiobook are on sale. Print is forthcoming December 15, 2026.
Reader code SHOWME20. 20% off for 12 months.
Consensus, by product family. The cards are the eighteen-month totals. The month-by-month grid is below.
Demand $58,018,125 (145 units).
Supply $58,018,125 (145 units).
Ending inventory $4,001,250 (10 units).
Gap $0.
Demand $34,640,000 (433 units).
Supply $34,640,000 (433 units).
Ending inventory $1,600,000 (20 units).
Gap $0.
Demand $30,729,600 (198 units).
Supply $25,142,400 (162 units).
Ending inventory $0 (0 units).
Gap $5,587,200.
Demand $23,111,075 (325 units).
Supply $23,111,075 (325 units).
Ending inventory $497,777 (7 units).
Gap $0.
Demand $19,322,268 (833 units).
Supply $14,195,952 (612 units).
Ending inventory $0 (0 units).
Gap $5,126,316.
Demand $27,075,270 (290 units).
Supply $27,075,270 (290 units).
Ending inventory $1,120,356 (12 units).
Gap $0.
? November 2025 through October 2026. Each point is the demand plan, the actual demand, and the capacity limit.
? November 2026 through April 2028 · company demand dollars by month. The line is company demand dollars.
? November 2026 through April 2028 · company supply and inventory dollars by month. A month missing supply or inventory is left off. It is not drawn as zero. The lines are company supply dollars and ending inventory dollars.
Each card is one family in one month. Demand is what you plan to sell. Supply is what you can make. Inventory is what you will hold. Nothing here posts.
This table scrolls sideways on a narrow screen.
| Family | Month | Demand units | Demand $ | Supply units | Supply $ | Inventory units | Inventory $ |
|---|---|---|---|---|---|---|---|
| Process skids | November 2026 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | December 2026 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | January 2027 | 7 | $2,800,875 | 7 | $2,800,875 | 10 | $4,001,250 |
| Process skids | February 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | March 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | April 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | May 2027 | 9 | $3,601,125 | 9 | $3,601,125 | 10 | $4,001,250 |
| Process skids | June 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | July 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | August 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | September 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | October 2027 | 9 | $3,601,125 | 9 | $3,601,125 | 10 | $4,001,250 |
| Process skids | November 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | December 2027 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | January 2028 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | February 2028 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | March 2028 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Process skids | April 2028 | 8 | $3,201,000 | 8 | $3,201,000 | 10 | $4,001,250 |
| Pressure vessels | November 2026 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | December 2026 | 23 | $1,840,000 | 23 | $1,840,000 | 20 | $1,600,000 |
| Pressure vessels | January 2027 | 22 | $1,760,000 | 22 | $1,760,000 | 20 | $1,600,000 |
| Pressure vessels | February 2027 | 23 | $1,840,000 | 23 | $1,840,000 | 20 | $1,600,000 |
| Pressure vessels | March 2027 | 24 | $1,920,000 | 24 | $1,920,000 | 20 | $1,600,000 |
| Pressure vessels | April 2027 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | May 2027 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | June 2027 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | July 2027 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | August 2027 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | September 2027 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | October 2027 | 25 | $2,000,000 | 25 | $2,000,000 | 20 | $1,600,000 |
| Pressure vessels | November 2027 | 24 | $1,920,000 | 24 | $1,920,000 | 20 | $1,600,000 |
| Pressure vessels | December 2027 | 23 | $1,840,000 | 23 | $1,840,000 | 20 | $1,600,000 |
| Pressure vessels | January 2028 | 23 | $1,840,000 | 23 | $1,840,000 | 20 | $1,600,000 |
| Pressure vessels | February 2028 | 24 | $1,920,000 | 24 | $1,920,000 | 20 | $1,600,000 |
| Pressure vessels | March 2028 | 23 | $1,840,000 | 23 | $1,840,000 | 20 | $1,600,000 |
| Pressure vessels | April 2028 | 24 | $1,920,000 | 24 | $1,920,000 | 20 | $1,600,000 |
| Heat-exchange bundles | November 2026 | 11 | $1,707,200 | 9 | $1,396,800 | 13 | $2,017,600 |
| Heat-exchange bundles | December 2026 | 11 | $1,707,200 | 9 | $1,396,800 | 11 | $1,707,200 |
| Heat-exchange bundles | January 2027 | 10 | $1,552,000 | 9 | $1,396,800 | 10 | $1,552,000 |
| Heat-exchange bundles | February 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 8 | $1,241,600 |
| Heat-exchange bundles | March 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 6 | $931,200 |
| Heat-exchange bundles | April 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 4 | $620,800 |
| Heat-exchange bundles | May 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 2 | $310,400 |
| Heat-exchange bundles | June 2027 | 12 | $1,862,400 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | July 2027 | 12 | $1,862,400 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | August 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | September 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | October 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | November 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | December 2027 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | January 2028 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | February 2028 | 10 | $1,552,000 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | March 2028 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Heat-exchange bundles | April 2028 | 11 | $1,707,200 | 9 | $1,396,800 | 0 | $0 |
| Piping spools | November 2026 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | December 2026 | 17 | $1,208,887 | 17 | $1,208,887 | 7 | $497,777 |
| Piping spools | January 2027 | 17 | $1,208,887 | 17 | $1,208,887 | 7 | $497,777 |
| Piping spools | February 2027 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | March 2027 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | April 2027 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | May 2027 | 19 | $1,351,109 | 19 | $1,351,109 | 7 | $497,777 |
| Piping spools | June 2027 | 19 | $1,351,109 | 19 | $1,351,109 | 7 | $497,777 |
| Piping spools | July 2027 | 19 | $1,351,109 | 19 | $1,351,109 | 7 | $497,777 |
| Piping spools | August 2027 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | September 2027 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | October 2027 | 19 | $1,351,109 | 19 | $1,351,109 | 7 | $497,777 |
| Piping spools | November 2027 | 19 | $1,351,109 | 19 | $1,351,109 | 7 | $497,777 |
| Piping spools | December 2027 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | January 2028 | 16 | $1,137,776 | 16 | $1,137,776 | 7 | $497,777 |
| Piping spools | February 2028 | 17 | $1,208,887 | 17 | $1,208,887 | 7 | $497,777 |
| Piping spools | March 2028 | 18 | $1,279,998 | 18 | $1,279,998 | 7 | $497,777 |
| Piping spools | April 2028 | 19 | $1,351,109 | 19 | $1,351,109 | 7 | $497,777 |
| Spare kits | November 2026 | 47 | $1,090,212 | 34 | $788,664 | 26 | $603,096 |
| Spare kits | December 2026 | 45 | $1,043,820 | 34 | $788,664 | 15 | $347,940 |
| Spare kits | January 2027 | 44 | $1,020,624 | 34 | $788,664 | 5 | $115,980 |
| Spare kits | February 2027 | 43 | $997,428 | 34 | $788,664 | 0 | $0 |
| Spare kits | March 2027 | 45 | $1,043,820 | 34 | $788,664 | 0 | $0 |
| Spare kits | April 2027 | 47 | $1,090,212 | 34 | $788,664 | 0 | $0 |
| Spare kits | May 2027 | 49 | $1,136,604 | 34 | $788,664 | 0 | $0 |
| Spare kits | June 2027 | 50 | $1,159,800 | 34 | $788,664 | 0 | $0 |
| Spare kits | July 2027 | 47 | $1,090,212 | 34 | $788,664 | 0 | $0 |
| Spare kits | August 2027 | 46 | $1,067,016 | 34 | $788,664 | 0 | $0 |
| Spare kits | September 2027 | 47 | $1,090,212 | 34 | $788,664 | 0 | $0 |
| Spare kits | October 2027 | 49 | $1,136,604 | 34 | $788,664 | 0 | $0 |
| Spare kits | November 2027 | 48 | $1,113,408 | 34 | $788,664 | 0 | $0 |
| Spare kits | December 2027 | 44 | $1,020,624 | 34 | $788,664 | 0 | $0 |
| Spare kits | January 2028 | 43 | $997,428 | 34 | $788,664 | 0 | $0 |
| Spare kits | February 2028 | 44 | $1,020,624 | 34 | $788,664 | 0 | $0 |
| Spare kits | March 2028 | 47 | $1,090,212 | 34 | $788,664 | 0 | $0 |
| Spare kits | April 2028 | 48 | $1,113,408 | 34 | $788,664 | 0 | $0 |
| Field install | November 2026 | 17 | $1,587,171 | 17 | $1,587,171 | 12 | $1,120,356 |
| Field install | December 2026 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
| Field install | January 2027 | 15 | $1,400,445 | 15 | $1,400,445 | 12 | $1,120,356 |
| Field install | February 2027 | 15 | $1,400,445 | 15 | $1,400,445 | 12 | $1,120,356 |
| Field install | March 2027 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
| Field install | April 2027 | 17 | $1,587,171 | 17 | $1,587,171 | 12 | $1,120,356 |
| Field install | May 2027 | 17 | $1,587,171 | 17 | $1,587,171 | 12 | $1,120,356 |
| Field install | June 2027 | 17 | $1,587,171 | 17 | $1,587,171 | 12 | $1,120,356 |
| Field install | July 2027 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
| Field install | August 2027 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
| Field install | September 2027 | 17 | $1,587,171 | 17 | $1,587,171 | 12 | $1,120,356 |
| Field install | October 2027 | 17 | $1,587,171 | 17 | $1,587,171 | 12 | $1,120,356 |
| Field install | November 2027 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
| Field install | December 2027 | 15 | $1,400,445 | 15 | $1,400,445 | 12 | $1,120,356 |
| Field install | January 2028 | 15 | $1,400,445 | 15 | $1,400,445 | 12 | $1,120,356 |
| Field install | February 2028 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
| Field install | March 2028 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
| Field install | April 2028 | 16 | $1,493,808 | 16 | $1,493,808 | 12 | $1,120,356 |
Product names on this page are trademarks of their respective owners. PGOS and The 80/20 Institute are not affiliated with, sponsored by or endorsed by them.
Help · What's new · Accessibility · Language
This is the monthly cycle. Demand, supply, inventory, a reconciliation, then the executive meeting.
1 of 3
Speak, then edit the words before you save.
This uses the microphone in your browser. We ask only when you press Speak. The audio is not uploaded and not stored. Only the text you keep is saved with the form.
Confirm?
Shortcut: Alt+M while you are in a field. Press-to-talk stops when you release M.